Type the delivery details at the plant and the pouring details at site, or leave the card empty to print a blank one. Material per batch = material per cum × concrete quantity per batch, and total concrete quantity = quantity per batch × no. of batches, are worked out as you type. Typed values are saved for this project.
| CONCRETE DELIVERY AND POURING CARD | |||||
| DELIVERY CARD | |||||
Location & Type of Structure: | Date: | ||||
Element of Structure: | W/C Ratio: | ||||
Grade of Concrete: | Admixture type: | ||||
Type of Cement: | Max Agg. Size: | ||||
| Description | Cement | Aggregate | Sand | Water | Admixture |
Concrete Quantity per batch in cum.: | No.of batches carried: | ||||
Starting Time of mixing 1st batch: | Finish time of mixing last batch: | ||||
Slump at batching plant: | Time of despatch: | ||||
Total Concrete Quantity in cum.: | Transit mixer no: | ||||
| Remarks : | |||||
|
Name:
Date:
Contractor's Representative
|
Name:
Date:
Concessionaire's/PMC Representative
|
Name:
Date:
IE's Representative
|
| POURING AT SITE | |||||
Concrete pouring method: | Pouring Starting Time: | ||||
Transit mixture arrival time: | Pouring Finishing Time: | ||||
Slump at pouring site: | No.of Cubes taken: | ||||
Weather condition: | |||||
|
Name:
Date:
Contractor's Representative
|
Name:
Date:
Concessionaire's/PMC Representative
|
Name:
Date:
IE's Representative
|